Oriental Square by OSI Holdings is undergoing steady transformation. Glass installation and exterior stone cladding are progressing rapidly, remaining firmly on track for handover in Q4 2025.

Key milestones:
1. Structure & Finishing:
• Structure: 100% completed
• Finishing: Brickwork 98%, plastering 95%, other finishing works 70%
2. Elevators:
• Elevator installation completed. Access control gate installation and elevator certification procedures are currently in progress.
3. MEP & Fire Protection:
• MEP systems: Basement works 98% complete; upper floors 95% (connection works in progress).
• Fire protection systems: 96% of works completed.
4. Façade:
• Glazing package: 100% of the glass and 100% of the aluminum have arrived in Vietnam. On-site installation has reached 50% and is expected to be completed from the 8th floor to the roof by 05/07.
• Stone cladding: 100% of exterior stone and 100% of elevator stone have been delivered; exterior stone installation progress is at 55%.
5. Show Unit:
• The show unit is scheduled for full completion after 5 July.
Stay tuned for more exciting updates from the project!



For detailed information or to schedule a visit, please contact our Hotline — Oriental Square by OSI, which is ready to help you find your ideal workspace.
Leasing Enquiries, please contact:
Address: Plot H2CC1 - Central area of Tay Ho Tay urban area, Xuan Tao, Bac Tu Liem, Hanoi
Website: https://oriental-square.com.vn/
Hotline: 0932 03 86 66